Ergon Energy network · 4818

Solar export limits in Bushland Beach

Mostly available

Most of Bushland Beach still has export headroom. 88% of local transformers with published data have at least 20% of their export capacity available, but 12% are getting tight.

That's the suburb-level picture. Export limits are set per transformer, and a street can differ from the one behind it, so check your own address to get the answer that applies to you.

49
transformers with published data within 1.5 km
88%
have 20% or more of their export capacity still available
166 kW
median export capacity still available per transformer
12%
are getting tight or constrained (under 20% left)
Solar export checker

Check your Bushland Beach address

Type your street address and we'll look up the Ergon Energy transformer that supplies it on Energy Queensland's capacity map, live.

The local picture

How Bushland Beach's transformers are tracking

Ergon Energy colours every transformer by how much of its solar export capacity is still free. This is the mix for the 59 transformers within 1.5 km of Bushland Beach.

  • 40 to 100% available34
  • 20 to 40% available9
  • 10 to 20% available3
  • 5 to 10% available0
  • under 5% available3
  • no published data10

Bushland Beach is supplied by Ergon Energy, the regional network that covers Queensland outside the south-east corner. Ergon's rules for small solar systems are the same as Energex's: a basic connection allows 5 kW of export per phase, and a Dynamic Connection can lift that to 10 kW per phase when the local network has room.

Regional feeders are often longer than city ones, so distance from the transformer matters more. Two houses on the same transformer can be offered different limits. That's why the checker looks at your specific address rather than the suburb as a whole.

1 of the 49 transformers with data (2%) are already curtailing exports for part of a typical day. On those, a Dynamic Connection is the difference between exporting most of the day and being capped.

Upstream headroom

The nearest zone substation, BLACKRIVER 66/11KV SUB (4.5 km away), reports 42.6 MVA of export capacity available against a 56 MVA rating. Street-level transformers, not the substation, are the usual bottleneck.

Source

Energy Queensland Network Load & Export Capacity Map, snapshot taken 15 September 2026. Indicative only; limits are confirmed when the network assesses a connection application.

Questions from Bushland Beach

Export limits in Bushland Beach, answered

Can I export solar to the grid in Bushland Beach?
In most cases, yes. Of the 49 local transformers with published data, 88% still have at least 20% of their export capacity available, which normally means the standard 5 kW per phase export limit applies. 12% are getting tight or constrained, so it's worth checking your exact address above.
What export limit will I get in Bushland Beach?
On a basic Ergon Energy connection it's 5 kW per phase: 5 kW for a single-phase home and 15 kW on three-phase. A Dynamic Connection can raise that to 10 kW per phase when the network has room. On a transformer that's nearly full, a new fixed connection may be limited to 1.5 kW, which is another reason to ask for a Dynamic Connection.
Where does this data come from?
From Energy Queensland's public Network Load & Export Capacity Map, which Ergon Energy publishes for engineers and installers. The suburb figures on this page are a snapshot of the map taken on 15 September 2026 for transformers within 1.5 km of Bushland Beach. The address checker queries the map live.
Is a battery worth it if my export is limited?
Usually the case for a battery gets stronger, not weaker. Export limits cap what you sell back at a low feed-in rate; a battery stores that power for the evening when you'd otherwise buy it at full price. We model both options with your bill before recommending anything.